Plat Development

This Plat development project started wtih raw land was wooded with a stream running through it. The Land was cleared, then the temporary erosion controls were installed. The installation of the sewer involved connecting to an Live Flowing Sanitary Sewer Main. The man holes were installed, then the lot services were installed. Next, the Storm Drainage system was installed. This involved excavating for and building of a very large vault. Next the water supply sytem was installed. Then the final grading for streets and sidewalks took place.

 

 
Project Photos

View Larger Image
Caption: This is the land as we are clearing it.
 

View Larger Image
Caption: This is what it looks like after we have cleared it.
 

View Larger Image
Caption: This picture is of the machines changing the grade of the land.
 

View Larger Image
Caption:
 

View Larger Image
Caption: Here, you can see a man hole getting ready to be slid down into the ground inside the protection of a shoring shield.
 

View Larger Image
Caption: This is an overview of the job site that let's you see the scope of the project.
 

View Larger Image
Caption: Here you can see the lay out for the large vault beginning
 

View Larger Image
Caption: Here you can see the land being prepared for a large storm water vault.
 

View Larger Image
Caption: This is more preparation for the vault
 

View Larger Image
Caption: You can see the elevation for the bottom of the vault here.
 

View Larger Image
Caption: This is the final digout before the bottom of the vault will be poured.
 

View Larger Image
Caption: In this picture, the bottom of the vault has been poured and the sides are being formed in.
 

View Larger Image
Caption: This shows the progress of the sides of the vault as they are being formed.
 

View Larger Image
Caption: This shows the actual forms around the rebar wall structures.
 

View Larger Image
Caption: This is just before the sides were poured
 

View Larger Image
Caption: This shows the side walls after the forms have been removed.
 

View Larger Image
Caption: Here is the vault with all the forms removed
 

View Larger Image
Caption: This is the preparation of the second half of the vault
 

View Larger Image
Caption: This is the preparation for the bottom of the next half of the vault
 

View Larger Image
Caption: The second half of the vault has been poured and the top of the vault is being sealed
 

View Larger Image
Caption: This shows the detail of how the vault is sealed
 

View Larger Image
Caption: This is the completed vault that will be buried